Existing grey shell warehouse building. New partition walls to create spec office. New architectural and MEP. New electrical meter 200A 3phase. Deferred fire sprinklers. Results in CofC.
Existing grey shell warehouse building. New partition walls to create spec office. New architectural and MEP. Approved as Noted: All roof-mounted equipment shall be 100% screened per Mesa Zoning Ordinance Section §11-30-9. Deferred fire sprinklers. Results in CofC.
Group B and S-1 occupancies. Type V-B construction. 16,650 SF. Occupant load 77. Existing grey shell building. New partition walls to create spec office space in warehouse suite. New architectural and MEP. Deferred fire sprinklers. Results in CofO.
Group M occupancy. Type V-B construction. 2,290 SF. Occupant load 38. New CofO permit for an existing suite. No work to occur under this permit. Results in CofO.
New 2406 SF single story residence with a 2 car garage at AVALON CROSSING. Includes a new water, electric and gas meter. Includes an option of a tandem garage. See permit MST26-06635 for addenda - Code update 2024
PLUMBING PERMIT TO REPLACE EXISTING WET SPACE WITH NEW SHOWER IN MASTER BATHROOM. NEW VALVE AND PREFABRICATED ACRYLIC WALLS. NO STRUCTURAL CHANGES. NEW INSTALLATIONS WILL TIE INTO EXISITING PIPING. NO CHANGE TO OVERALL SQUARE FOOTAGE. NO OTHER WORK UNDER THIS PERMIT. ALL WORK TO COMPLY WITH 2024 IRC AND 2023 NEC.
CITY OF MESA ZONING CLEARANCE PERMIT ONLY FOR INSTALLATION OF 24-FT X 48-FT **** ABOVE-GROUND SET HERE COMES THE SUN MANUFACTURED HOME SERIAL NO. ********* WITH A/C. NO GAS. 200AMP PANEL UPGRADE. ONE 12-FT X 48-FT ATTACHED AWNING PER ICC ESR 1398. AWNING ENG PROVIDED BY CARL PUTNAM #39702. ACCESSORY STRUCTURE ROOF AREAS DO NOT EXCEED THE 100% MH FLOOR AREA. NO OTHER ACCESSORY STRUCTURES AT THIS TIME. MINIMUM TWO 9-FT X 18-FT PAVED UNOBSTRUCTED PARKING SPACES ARE REQUIRED BEHIND FRONT SETBACK ONE
Construction of a new 1280 square foot detached garage at existing SFR. VB construction including electrical & mini-split unit. Minimum required building inspections: Footing, stem, strap and shear, mechanical rough in, electric rough in, insulation, framing, mechanical final, electric final, and final. If needed, underground electrical.
Pallet Rack Installation. Pallet Rack Installation. HPCS plan.
Install one single faced illuminated multi-tenant monument sign. Ref CSP BOA25-00058. Results in CofC.
Install one single faced illuminated multi-tenant monument sign. Results in CofC.
Install one (1) set of illuminated pan channel letters with logo 33 sq ft on south elevation. LOGO SHIMA SUSHI
360 sq ft non-livable detached accessory structure to existing SFR. VB construction. No Electrical, plumbing or mechanical. Minimum required building inspections: Strap and shear, framing and final.
Install (1) 16.71 sq ft front lit channel letters G1 VAPES AZ.
Running electrical to shed from pre existing panel
dual-phased development that includes a retail component (Phase 1) and a multifamily component (Phase 2) and includes private roadways that run through the development
The prior permit PMT24-19645 was not properly amended to make the bedroom a storage. Therefore, I have to relabel the bedroom as a storeroom, as seen in the attached plans. No new construction will actually take place.
dual-phased development that includes a retail component (Phase 1) and a multifamily component (Phase 2) and includes private roadways that run through the development
THIS DOCUMENTATION IS FOR A TENANT IMPROVEMENT TO CONVERT TWO FORMER SUITES INTO A SINGLE SUITE FOR A SHOE STORE. THIS INCLUDES NEW FINISHES. THE RESTROOM HAS BEEN ALTERED IN THE PAST AND WILL BE RESTORED TO ADA COMPLIANCE. NO UTILITY UPGRADES ARE REQUIRED. SIGN IS BY SEPARATE PERMIT.
Installation of one set of reverse pan channel letters (top row) and front lit pan channel letters (bottom row) on brushed aluminum backer board. White, black, metallic, and turquoise faces, illuminated with white LEDs. Flush and stud-mounted to 3mm contour cut aluminum backer board and raceway which is mounted to the building and secured with anchors, screws, and bolts. 3" black trim cap, 3" black returns.
Provide activities of daily living support for 1-4 residents 24 hour/day 7 days/week as an adult foster care home.
Installation of two different sets of front-lit pan channel letters. White and magenta acrylic faces illuminated with white LEDs. 3" black returns, 3/4" black trim cap. Secured flush mounted to the building with anchors, screws, and bolts.
Replace the current freestanding sign with a new one.
Installation of one set of front lit pan channel letters and logo box. White, black, and red acrylic faces. 3" black returns, 3/4" black trim cap. Illuminated with white LEDS for 'RONIN' and red LEDs for 'GAMES'. Flush mounted to the building secured with anchors, bolts, and screws.
Installation of a Fire Alarm System with ANSUL Hood, Fire Sprinkler & CO2 Monitoring.
Adding a 2 car carport to rear of house to comply with the As-Built permits they are applying for. Enclosed Garage and made livable
Adding a new sprinkler monitoring system with heat detectors in the attic.
As Built Plans converted the covered patio and a portion of the AZ. Room into a laundry room for the main house including bedroom and bathroom. As built plans for ADU converted the 2 car garage into a family room/ kitchenette. Took the existing storage /Laundry room and added a bathroom tot that area and took the remaining square footage from the Az Room and converted it to a bedroom. Attic access from the existing garage remain in place to support both areas.
build new addition to existing park model with elect and plumbing
Installation of a 8.200kW expansion/system add-on to existing Roof mounted Photovoltaic System with a Tesla Powerwall3 Battery and a Tesla backup gateway